Pittfalls and Fixes For New Projects During the Holiday Season

Published Date: August 15, 2025

Launching a new project in October or November may look feasible on paper, but the reality on-site is much different. The holiday season brings weather interruptions, reduced city staffing, limited engineering availability, and stretched subcontractor schedules. For general contractors and construction companies, that means even simple tasks like getting a test scheduled or securing a sealed letter can suddenly take weeks longer than expected.

The issue isn’t that new projects can’t begin late in the year. It’s that without proper engineering planning, they tend to stall. And when projects stall in November or December, they rarely pick back up until January. This downtime isn’t just lost momentum; it’s lost money, frustrated owners, and reputational risk for the GC. In this article, we’ll break down the most common pitfalls of starting late-season projects and how the right approach can keep things moving.

Pitfall 1: Delayed Approvals and Inspections

City offices and inspectors go into holiday schedules as early as mid-November. A request that might normally be cleared in days can take weeks. This creates a ripple effect. Permits can’t close, site work pauses, and crews are left idle.

Fix: Partner with your engineering firm to provide interim documentation. Sealed letters, condition reports, and early inspections can bridge the gap when city schedules slow down, allowing work to continue instead of waiting for approvals.

 

Pitfall 2: Weather Disruptions Compound Delays

South Florida’s storm season overlaps with the holiday calendar. Rain delays pile up at the worst possible time, often making it impossible to perform or pass inspections. Projects that were already tight on schedule can quickly fall weeks behind.

Fix: Build flexibility into your inspection schedule. Coordinate with your engineer to set alternative testing days or multiple inspection windows, so a single storm doesn’t derail the timeline.

Pitfall 3: Crew and Subcontractor Availability Shrinks

By late in the year, many subcontractors are either booked solid or planning for time off. That means fewer hands on deck just as deadlines become critical.

Fix: Prioritize engineering milestones that unlock progress for subs. For example, securing a structural observation or uplift test early lets other trades proceed while you’re waiting on less urgent items.

 

Pitfall 4: Projects Spill Into the New Year

The biggest risk of starting a project late isn’t just the holidays themselves, it’s the rollover effect. Once a project misses its December target, it often can’t resume until January, when engineers, inspectors, and crews are returning to heavy backlogs.

Fix: Treat October as your real deadline. Work with PES to identify the engineering tasks that must be completed this month to prevent your project from being pushed into 2026.

 

Starting a project in the last quarter of the year isn’t impossible, but it requires proactive planning. By securing engineering support early, confirming inspection dates, and having sealed documentation ready, GCs can protect themselves against the seasonal crunch. The contractors who adapt don’t just survive the holiday season, they finish stronger, with fewer delays and happier clients. A project launched in October can succeed if you plan like the holidays start tomorrow. The ones who wait are still waiting when January comes around.